Community Center build - day 4!

DAY 4

 

Work is progressing at a fast pace on the community center. The metal framework around the hall, utility room and storeroom was completed by the end of Day 3. 

Day 4 saw the team finish attaching  the iron sheets up to a height of three meters, on the outside walls and one meter, on the inside. Work then began on reinforcing the space, between the walls, with a cement and pit-sand mixture.  With the team working from the crack of dawn to sunset each day, it won’t be long before the job is completed.

 

 Stay tuned for further updates!